Grants:Project/Daimona Eaytoy/AbuseFilter overhaul/Finances
This project is funded by a Project Grant
proposal | people | timeline & progress | finances | midpoint report | final report |
Budget
[edit]Below is your approved budget. Please use this table to keep track of actual funds spent for each line item and list the difference from the approved budget at the end of the grant period.
Expense | Approved amount | Actual funds spent | Difference |
Development time (bugfix, architecture refactoring, new features) | 24000 USD | 24000 USD | ∅ |
Total | 24000 USD | 24000 USD | ∅ |
Request changes
[edit]We understand that sometimes plans change. Please use this button to request approval for changes to your grant’s budget while your project is in progress. Any variation of 20% or more to any line item in your budget must be approved by staff here before you make the change (for projects with budgets of $15,000 or more, the accepted variance is 10%).
Budget change request
[edit]Relocation of the 70 hours originally planned for "Implementing a new feature", into the rest of the "Pure development" part. The "Implementing a new feature: shared variables" goal would be removed.
Rationale
[edit]This request is a direct consequence of two situations. First of all, we investigated the implementation details of the "shared variables" part. The conclusion is that, in order to properly implement it, we would require a schema change to add an additional table to the database. Given that:
- Applying schema changes on WMF sites is a lengthy process that requires a noticeable effort from the DBAs, and possibly quite a lot of time;
- Without this schema change, we cannot deliver a complete product;
- Our project is set to end on February 28th, and further extending the duration might not be possible for us;
I'd like to remove this specific goal from the project, which also means we would end up with 70 (+rounding) unallocated hours.
The second thing is that the progress so far ended up taking more hours than what we budgeted for. In particular, both of us have already spent the full budget (more or less), rounding included. This means that those 70 (+r) hours were already spent as part of the architecture overhaul and the bugfixing part, hence I'd like to formally relocate them as well. Thank you, --Daimona Eaytoy (talk) 16:19, 22 February 2021 (UTC)
Approved
[edit]Daimona Eaytoy, this budget change request is approved, reallocating 70 hours of labor from implementing a new feature to pure development. -Marti (WMF) (talk) 20:17, 4 March 2021 (UTC)